Project Update – Teynham Parochial C of E Primary School

Fantastic to see the progress made at Teynham Parochial C of E Primary School on one of our first site visits back after the Christmas break!

The main roofing works are now complete, mechanical plant has been lifted up ready for future works and cladding is complete on three elevations of the main building. Internally the internal dry-lining, first-fix installations and ventilation works are progressing well.

Looking forward to seeing the sliding screen track system in place in the main hall and the PV Panels safely on the roof in the coming period!

Woodley Coles LLP are providing Quantity Surveying Services for Kent County Council working alongside WW Martin Ltd, Bailey Partnership and Innovaré Offsite Limited.