Project Update – DWDR Stage 3B

Works are well underway on the Marine Civils & Reclamation contract as part of Dover Western Docks Revival (DWDR) Stage 3B at Port of Dover. The Principal Contractor, Boskalis Westminster Ltd. and McLaughlin & Harvey Ltd Joint Venture (BWMH JV), are progressing numerous activities across the site in preparation for reclamation this September.

Current activities include: placing the core material for the Wick Channel closure bund up to mean high water springs level using a long reach excavator, services protection across the Wellington Dock using a dive team, marine and landside demolition and mobilisation of marine plant in readiness for the reclamation.

Woodley Coles are delighted to be supporting the Port of Dover with this project.