Dartford Town Centre Regeneration Phase 2a

Dartford Town Centre Regeneration Phase 2a aimed to create a better pedestrian experience through Instone Road and Lowfield Street. This was achieved by installing new pedestrian crossings, removing the unsightly underpasses, widening the movement corridor for pedestrians, laying high-quality granite paving and kerbs and creating planting areas throughout.

The project was completed in March 2024 with Phase 2b commencing in Winter 2024.

Landscape Architect

Project Centre

Contractor

Walker Construction

Civil Engineer

Wilde Consulting Civil and Structural Engineers

Photos by

Barlotte

Woodley Coles were engaged by the Dartford Borough Council to provide a RIBA Stage 4 cost estimate for the scheme and support their Project Manager with post-contract commercial duties including monthly valuations, cost reporting and managing compensation events.